Your browser does not support JavaScript!
The Challenge

Following a site visit to plan the project we calculated that a 2.7m clearance would be needed to safely lift the load down from the second floor loading bay, which combined with the lifting capacity of 3.2 tonnes and the need for fast installation was a challenge.

The Solution

The lifting solution we planned and presented to the customer was a run out crane with electric chain hoist which would ensure that loads could be safely lifted up and far enough out away from the building before being lowered into the awaiting trailers.

The system consisted of an 11.5m monorail main beam completed with joint and end stops that was fixed to the buildings existing steelwork. Below the main beam there

was a hand geared 9 metre runout beam featuring 2.7 metre length cantilever.

The runout beam was fitted with a Eurochain VR16 electric chain hoist providing the required 3.2 tonne load capacity, 8 metres height of lift and complete with a motorised travelling trolley. The VR electric chain hoist was supplied and installed complete with radio control.

MAKE AN ENQUIRY FOR A RUN OUT CRANE